Beginning on Sunday, Oct. 26, removal and replacement of the existing concrete paving in the West Victorian intersection will begin. Once the removal has been completed, they will begin placement of the new concrete pavement throughout the intersection beginning Monday, Oct. 27 with an anticipated reopening of the intersection late in the day Wednesday, Oct. 29.
This work will require that the intersection be completely closed from 8 a.m. on Sunday, Oct. 26, through approximately 5 p.m. on Wednesday, Oct. 29. This will require a complete closure of Mainstreet, with no vehicular traffic on Mainstreet between the west Victorian intersection and Pikes Peak Drive to the west. Pedestrian traffic will be allowed for access to downtown businesses.
ALL of Mainstreet traffic will be diverted to the following detours:
Westbound traffic from East Mainstreet, wanting to use Mainstreet, will be detoured at Pikes Peak to the south. West bound traffic will also be able to turn north on East Victorian and proceed to Longs Way.
Eastbound Mainstreet traffic will be detoured to the south at the Wells Fargo bank entrance through the parking lot area and may either proceed to Rodeo Drive or to Pikes Peak and go north or south on Pikes Peak.
Traffic that is southbound on Longs Way will not be able to get through the West Victorian and Mainstreet intersection, but will still be able to access parking at O'Brien Park, the 20-Mile Building or the Parker Station parking area from either West Victorian or East Victorian.
Please be advised that Mainstreet in the downtown area will not be reopened to traffic until the afternoon on Wednesday, Oct. 29. It is anticipated that both the Victorian loop and Mainstreet will re-open at that time. Please understand that these time frames are weather dependent, but every reasonable effort will be made to meet this schedule.
Detour signing will be in-place as of 7 a.m. on Sunday morning, Oct. 26. Please seek alternate routes for access to Parker Road and to Pine Drive. Visit the Town's Web site at www.parkeronline.org for alternate routes around the construction area.
Businesses in the downtown area can still be accessed by parking in public areas on Pilgrims Place off Pikes Peak Drive, behind the Parker Station building, the 20-Mile building or O'Brien Park.
Welcome to the Town of Parker Colorado (unofficial) Blog. Find events, concerts, sports information, local entertainment,add restaurant or movie reviews, popular Parker links, and discuss Parker Issues. Also see the Things to do for Kids in Parker CO Blog.
Showing posts with label mainstreet Construction. Show all posts
Showing posts with label mainstreet Construction. Show all posts
Thursday, October 23
Friday, October 10
Ongoing Saga of Mainstreet Construction
Per the Town of Parker -
"Next week, the contractor will begin removal of the existing sidewalk from Pikes Peak west, on the south side of Mainstreet. They anticipate starting the placement of the new sidewalk in this area by Thursday following installation work by the lighting and landscape subcontractors of their respective infrastructure.
They also plan to continue the curb and gutter removal and replacement from West Victorian to the west, on the south side of the street. Traffic will continue to be shifted to detour routes as various lane closures will be needed during working hours. This will give them access to the eastbound lanes during the day. There are no complete Mainstreet closures anticipated this week.
The lighting and traffic system sub-contractor will be working on placing additional signal lights on the newly erected traffic signal poles, and they also will be placing lighting conduit and bases along the south side of Mainstreet west of Pikes Peak prior to sidewalk placement.
The irrigation and landscaping sub-contactor will be working in this same area, placing conduit for irrigation of the new trees that will eventually be placed along this section. They will also begin working on repairing the existing irrigation and landscaping that has been damaged during construction.
There will be traffic control devices and flagging personnel in the area during working hours to assist vehicular and pedestrian traffic. Please be aware that the flagging personnel are there for you're your safety. Please be courteous and respectful as you pass through the project.
If you are driving or walking in the construction area, please be aware of all the equipment and workers in the immediate construction area, and proceed with extreme caution.
Restricted parking areas along Mainstreet will continue on both sides of the street as the construction activities go on. Please continue parking in outlying areas or parking lots.
The sidewalk in the park area, along the north side of Mainstreet at O'Brien Park and on both sides of west Victorian is still somewhat restricted. If you are in the park, please stay on the park (north) side of the orange safety fence for your own safety. Please be very cautious when crossing Mainstreet, and if driving through Mainstreet, watch for pedestrians.
Thank you in advance for your patience during this important project."
"Next week, the contractor will begin removal of the existing sidewalk from Pikes Peak west, on the south side of Mainstreet. They anticipate starting the placement of the new sidewalk in this area by Thursday following installation work by the lighting and landscape subcontractors of their respective infrastructure.
They also plan to continue the curb and gutter removal and replacement from West Victorian to the west, on the south side of the street. Traffic will continue to be shifted to detour routes as various lane closures will be needed during working hours. This will give them access to the eastbound lanes during the day. There are no complete Mainstreet closures anticipated this week.
The lighting and traffic system sub-contractor will be working on placing additional signal lights on the newly erected traffic signal poles, and they also will be placing lighting conduit and bases along the south side of Mainstreet west of Pikes Peak prior to sidewalk placement.
The irrigation and landscaping sub-contactor will be working in this same area, placing conduit for irrigation of the new trees that will eventually be placed along this section. They will also begin working on repairing the existing irrigation and landscaping that has been damaged during construction.
There will be traffic control devices and flagging personnel in the area during working hours to assist vehicular and pedestrian traffic. Please be aware that the flagging personnel are there for you're your safety. Please be courteous and respectful as you pass through the project.
If you are driving or walking in the construction area, please be aware of all the equipment and workers in the immediate construction area, and proceed with extreme caution.
Restricted parking areas along Mainstreet will continue on both sides of the street as the construction activities go on. Please continue parking in outlying areas or parking lots.
The sidewalk in the park area, along the north side of Mainstreet at O'Brien Park and on both sides of west Victorian is still somewhat restricted. If you are in the park, please stay on the park (north) side of the orange safety fence for your own safety. Please be very cautious when crossing Mainstreet, and if driving through Mainstreet, watch for pedestrians.
Thank you in advance for your patience during this important project."
Tuesday, September 16
Mainstreet Construction... Will it EVER end??
And exactly how much are we paying for this??? And who decided we would??? Leave your rants here to share with the rest of us who are frustrated by not being able to get to the businesses we know and love... I could barely get into the Parker Day Spa yesterday due to the blocked street on mainstreet, the tree branch down in the middle of Pikes Peak, and then the construction guys from the giant victorian office building blocking the other side of the road?? Anyone else a little miffed??